Good morning, and thanks for opening this week’s briefing. Capital keeps chasing power. SpaceX put a $74 billion price tag on new campuses in Texas and Arizona, PPL’s Pennsylvania data center pipeline climbed past 35 GW, and an investment-grade hyperscaler committed $200 million up front for 600 MW at Fermi’s Project Matador. At the same time, Nvidia’s sudden leadership change and reported Samsung talks to acquire cooling maker Modine are reminders that the supply chain behind these builds is shifting as fast as the projects themselves. For vendors, demand is real, but timing and relationships matter more than ever. As always, hit reply if you want to talk any of this through.

Joseph H. Norris

Joe Norris  |  Managing Principal, Data Center Results

↑ Back to top
2

DCR Stat of the Week

35.3 GW
PPL’s advanced-stage data center pipeline in Pennsylvania
PPL reported on its Q3 earnings call that advanced-stage data center projects in its Pennsylvania territory grew by 3.5 GW from Q2, its 11th consecutive quarterly increase. Load signed under electric service agreements rose to about 11.4 GW, and 8.5 GW of that is now under construction, up 2 GW in a quarter. PPL also agreed commercial terms to supply about 2 GW of generation to a QTS campus in Salem Township, using two combined-cycle gas plants plus fuel cells and battery storage. Source: Data Center Dynamics, November 10, 2026.
↑ Back to top
3

Industry Updates & Big News

Big News

SpaceX commits more than $74 billion to data center campuses in Texas and Arizona

SpaceX announced on November 12 that it plans to invest more than $24 billion in a project in Texas’s Rio Grande Valley near its Starbase headquarters and about $50 billion in Cochise County, Arizona. The Texas project, a gas-fired power plant and supercomputing facility on a 444-acre tract between Boca Chica Boulevard and the Port of Brownsville, would generate its own power, and SpaceX pledged $220 million to expand Brownsville’s water supply. The Arizona site would use dry cooling. The Starbase City Commission is scheduled to consider a tax abatement agreement on December 9.

Source: The Hill, November 12, 2026; Data Center Dynamics, November 11, 2026

Leadership

Jensen Huang resigns as Nvidia CEO; CFO Colette Kress named interim chief executive

Nvidia announced on November 12 that Jensen Huang had stepped down as CEO and from the board, ending a 33-year tenure, after several days of scrutiny over reported personal relationships and related national security questions. CFO Colette Kress is serving as interim CEO while the board searches for a permanent successor, and longtime director Harvey Jones was named board chair. Nvidia shares fell more than 14% at one point during the day before recovering some ground. With Nvidia supplying the large majority of advanced AI accelerators, vendors should watch for any change in product roadmap or allocation priorities that could ripple into North American build schedules.

Source: Al Jazeera and Reuters, November 12, 2026

Power & Policy

BNEF: planned data center gas plants would lift U.S. power emissions about 10%

A BloombergNEF report released November 11 found that if all gas-fired plants announced so far for U.S. data center sites were completed, power-sector emissions would rise about 10% compared with 2025 levels. The report adds to a tense political backdrop. The same day, Senator Josh Hawley called on fellow Senate Republicans to pass a moratorium on new data centers. Expect on-site generation projects to face closer questions on emissions, permitting, and community benefits.

Source: Bloomberg, November 11, 2026; The Hill, November 12, 2026

↑ Back to top
4

New Builds, Deals & M&A

New Builds

New Build

Kraft Group eyes a 900 MW, $16 billion campus in Sutton, Massachusetts

A memo from Sutton’s town manager says the Kraft Group and Unified Global Packaging Group are planning a campus at Unified’s Parkway property. Phase one would be two buildings of about 250,000 sq ft and roughly 90 MW each, launching in 2029, with two more buildings a year through 2033 for about 900 MW at full build-out. The proposal is tentative, with no formal application yet, reclaimed water planned for cooling, and a town meeting vote targeted for May 2027.

Source: Data Center Dynamics, November 11, 2026

Under Construction

Fluidstack breaks ground on its Solis Arx campus in Wythe County, Virginia

AI cloud provider Fluidstack has begun construction on a 99-acre campus at Progress Park in southwest Virginia. The project is expected to exceed $1 billion in investment, with most phases complete by the end of 2027, about 1,000 construction jobs, and 75 permanent positions. It will use a closed-loop cooling system, and Fluidstack has said it will cover the cost of power infrastructure upgrades.

Source: Data Center Dynamics, November 10, 2026

Pipeline

QTS Caprock campus in Midland, Texas, targets about 1.2 GW with on-site gas

Aterio’s November U.S. industry update details QTS’s planned Caprock campus in Midland at roughly 1.2 GW across four 300 MW buildings, supported by on-site natural gas, with phased activation from late 2029 to September 2030. The same update tracks AWS’s 1,200 MW campus at Comanche Peak in Somervell County, Texas, which received a conditional ERCOT recommendation for a net metering arrangement with the nuclear plant.

Source: tED Magazine (Aterio release), November 10, 2026

Deals & M&A

M&A

Samsung in talks to acquire data center cooling maker Modine

Bloomberg reports that Samsung Electronics is in talks to acquire Modine Manufacturing, a U.S. maker of cooling systems for data centers, and that a deal could come together as soon as the coming weeks. No terms have been disclosed and talks may not result in a transaction. A completed deal would put one of North America’s key thermal management suppliers under a global electronics group, a shift cooling vendors and their channel partners should watch closely.

Source: Bloomberg, November 12, 2026

Power Deal

Hyperscaler commits $200 million up front for 600 MW at Fermi’s Project Matador

Fermi said an unnamed investment-grade hyperscaler agreed to a 600 MW power deal at Project Matador near Amarillo, Texas, providing $200 million up front plus $15 million under an early construction and site development agreement. The parties are also finalizing a $90 million structural steel and building materials purchase. A lease has not yet been signed, and Fermi confirmed its earlier lease with AI cloud TensorWave has been terminated.

Source: Data Center Dynamics, November 13, 2026

M&A

GridAI to acquire Wyoming gas producer Pronghorn Resources for an AI power platform

GridAI Technologies signed a definitive share exchange agreement to acquire Pronghorn Resources in Wyoming’s Powder River Basin. Pronghorn brings close to 100 MMcf per day of gross gas production, which GridAI estimates could fuel up to about 600 MW of gas-fired generation, plus more than 450 miles of owned pipeline and roughly 1,000,000 acres of mineral and leasehold interests. GridAI is targeting 300 MW of initial behind-the-meter power delivery in 2027, and the deal is expected to close on or before November 22.

Source: GridAI Technologies (GlobeNewswire), November 13, 2026

↑ Back to top
5

Technology Spotlight

Compute

Optical compute for AI inference: moving prefill off the GPU

Inference has two phases. Prefill processes the prompt and context and is compute-bound, while decode generates output tokens one at a time and is limited by memory bandwidth. Optical compute company Lumai is targeting prefill with its Iris Nova server, which uses light and passive optics to perform the matrix multiplications at the heart of inference while memory, control, and nonlinear functions stay electronic. Iris Nova runs in standard air-cooled racks, works with PyTorch and disaggregated serving frameworks such as vLLM and SGLang, and is now being deployed in an independent commercial test lab to gather system-level performance data.

Why it matters: North American operators are increasingly building to a fixed power envelope, and agentic workloads with long contexts push more of the inference load into prefill. If optical accelerators can handle that phase at a fraction of the power, operators could free GPU capacity for decode inside the same megawatts, with implications for rack density, cooling mix, and power distribution design in the next wave of inference-focused builds.

Source: Data Center Knowledge, November 6, 2026

↑ Back to top
6

Upcoming Conferences

EventWindowLocation
Gartner IT Infrastructure, Operations & Cloud Strategies ConferenceEarly December 2026Las Vegas, NV
PTC’27Mid January 2027Honolulu, HI
Data Center AmericasLate March to early April 2027Washington, DC
National Data Center Investment Conference and ExpoEarly May 2027Rockville, MD
Data Center WorldLate May 2027Nashville, TN
View the full DCR events calendar →

Dates shown are general windows. Please confirm exact dates on the DCR events calendar.

↑ Back to top