Weekly Industry Briefing
Week of November 11, 2026
1

A Note From Joe

Good morning, and thanks for opening this week’s briefing. The post-election picture is coming into focus. The Senate voted to take up a permitting bill that touches data centers, Texas’s governor-elect promised to keep new projects paused, and buyers are locking up power and land at record scale. Anthropic reportedly paid $3.4 billion for 1.7 GW of gas generators, Riot signed a 910 MW lease in Corsicana, and Lambda announced a $33.1 billion campus in Alabama. For vendors, the message is that demand has not slowed, but it is concentrating where power, permits, and community support line up. As always, hit reply if you want to talk any of this through.

Joseph H. Norris

Joe Norris  |  Managing Principal, Data Center Results

↑ Back to top
2

DCR Stat of the Week

$28B
Total contract value of Riot Platforms’ 910 MW AI data center lease in Corsicana, Texas
Riot signed a 15-year triple-net powered land lease covering its entire 332-acre Corsicana campus with an unnamed “leading Frontier AI Lab.” The lease averages about $1.8 billion a year and could reach about $54 billion if both five-year extensions are exercised. Delivery is phased: 400 MW in September 2027, 200 MW in January 2028, and 310 MW in July 2028. Riot will fund about $2 million per IT MW for site work and electrical infrastructure, while the tenant procures and operates the compute. Source: Riot Platforms (company release), November 4, 2026.
↑ Back to top
3

Industry Updates & Big News

Big News

Anthropic reportedly pays $3.4 billion for 1.7 GW of gas generators

Citing the Financial Times, Fortune reports that Anthropic took over generator commitments that San Antonio equipment supplier OnePWR Solutions had made with Caterpillar, covering 1.7 GW of heavy-duty natural gas generators. The deal also includes engineering and construction services to install the equipment, and the generators are expected to become available over the next two years. Fortune calls it the largest direct investment in power generation equipment by an AI company. Site locations were not disclosed, and neither company commented. Other reports say the agreement was reached in late September and only surfaced this week.

Source: Fortune, November 10, 2026, citing the Financial Times

Policy

Senate votes 73-25 to take up a permitting bill that covers data centers

On November 9 the Senate voted to formally take up a bipartisan bill sponsored by Senators Capito, Lee, Heinrich, and Whitehouse. As described by the Boston Globe, it would speed permitting reviews for data centers and other infrastructure, shorten timelines for large energy projects, and require data centers to pay for the energy they use. Sponsors hope to pass it in the lame-duck session. It has not passed either chamber, and House Minority Leader Hakeem Jeffries said the bill “falls short” in several areas.

Source: Boston Globe, November 9, 2026

Policy

Texas governor-elect Gina Hinojosa promises to keep new data centers paused

ABC13 Houston reports that governor-elect Hinojosa plans to pause construction of new data centers until new rules are in place. Her goals for the next legislative session include making data centers pay for themselves, full transparency, and putting water and power for Texans first. A political scientist quoted in the story notes that permitted projects already under construction or operating generally cannot be frozen, so the main impact falls on future projects. For suppliers with Texas pipelines, permitted and in-progress work looks steadier than early-stage opportunities.

Source: ABC13 Houston, November 6, 2026

↑ Back to top
4

New Builds, Deals & M&A

New Builds

New Build

Lambda plans the $33.1 billion Red Clay campus in Lowndes County, Alabama

Lambda announced the Red Clay Technology Center Campus near U.S. Highway 80 and Alabama Highway 21, with an estimated $33.1 billion investment in the state. Cloverleaf Infrastructure readied the site, and Alabama Power will supply power pending regulatory approval. Construction is expected to begin in the first quarter of 2027 and may take up to five years, with more than 1,000 construction jobs and more than 225 full-time roles. Baxtel reports a planned 1 GW, with room for 1.5 GW, and first operations targeted for late 2028.

Sources: Lambda (company announcement), November 4, 2026; Baxtel, November 5, 2026

New Build

Integra registers a 288,355 sq ft building at its 756 MW Quanah, Texas campus

A Texas Department of Licensing and Regulation filing registers the “Clocktower” network building, a single-story 288,355 square foot structure at 4628 Four Corners Road in Quanah, Hardeman County. The filing lists a build window from November 1, 2026 to December 31, 2028, and the planned campus totals 756 MW. Reports cite an $8 billion figure, though Construction Review notes it combines the building registration with a separately published $6.7 billion campus baseline.

Source: Construction Review Online, November 9, 2026

Proposed

SpaceX hosts a community meeting on a proposed 6 GW campus in Cochise County, Arizona

SpaceX held a community meeting on a proposal for about 747 acres in rural Cochise County near the Apache Generating Station, with nine AI data center buildings drawing up to 6 GW at full build-out. The special use application names Tombstone Resources LLC as applicant and proposes dry cooling to reduce water use. No decision has been made, and the county Planning and Zoning Commission will hold a formal public hearing on December 9.

Source: AZFamily, November 4, 2026

Deals & M&A

Deal

Google provides a credit backstop for TeraWulf’s Anthropic-leased Kentucky campus

Google signed credit support agreements for anticipated debt financing at TeraWulf’s Justified Data Campus in Hawesville, Kentucky, which carries about $19 billion in contracted lease commitments with Anthropic. Phased ready-for-service dates begin in late 2027 and run through the second quarter of 2028. TeraWulf also confirmed its guaranteed maximum price EPC agreement with Fluor for three buildings. No backstop dollar amount was disclosed. Riot’s 910 MW Corsicana lease, this week’s other headline deal, is covered in the Stat of the Week.

Source: Blackridge Research, November 4, 2026

↑ Back to top
5

Technology Spotlight

Power

Solid-state transformers and 800 VDC power for AI racks

As GPU racks head toward megawatt scale, the industry is moving from traditional low-frequency transformers and multiple conversion stages toward medium-voltage solid-state transformers (SSTs) that convert grid power to 800 VDC in a single stage. This week SolidUltra, a new French company, announced €3 million in funding for a modular SST it says reaches 98.5 percent efficiency with a 4x smaller footprint, targeting commercial launch in 2028. In October, DG Matrix introduced its Interport SST platform, which accepts up to 34.5 kVAC and outputs native 800 VDC for NVIDIA MGX-based AI factories.

Why it matters: 800 VDC changes what North American builds buy for the electrical room and white space, from switchgear and UPS to busway and rack power shelves. Fewer conversion stages mean less heat, smaller footprints, and potentially faster power delivery. The technology is early, so expect pilots and hybrid AC/DC designs before wide adoption, but suppliers should be building 800 VDC expertise now.

Sources: SolidUltra via GlobeNewswire, November 9, 2026; The Data Center Engineer, October 16, 2026 (background)

↑ Back to top
6

Upcoming Conferences

EventWindowLocation
Advancing Data Center Design & Engineering EastMid November 2026Herndon, VA
PTC’27Mid January 2027Honolulu, HI
Data Center AmericasLate March to early April 2027Washington, DC
National Data Center Investment Conference and ExpoEarly May 2027Rockville, MD
Data Center WorldLate May 2027Nashville, TN
View the full DCR events calendar →

Dates shown are general windows. Please confirm exact dates on the DCR events calendar.

↑ Back to top